Kalkbult, South Africa
Project key figures
Substructure-system: Fixed tilted
Modules: BYD polycrystalline
Inverter-system: SMA Inverters
Energy produced: 150,000 MWh per annum
112
Land use
(ha)
40
DC-capacity (MW)
20k
Households provided with energy
2390
Project yield (kWH)
Ownership and PPA
PPA with Eskom for a period of 20 years
Project development
Scatec Solar was awarded the 75 MW Kalkbult project in December 2011.
The Kalkbult site is the largest project awarded in the 1st bidding round in South Africa, accounting for 12% of overall volume. Scatec Solar initiated the development, partnering with Simacel a local project developing company.
Project Execution
The 75 MW power plant was completed in record time (January 2013 – September 2013) and was grid connected three months earlier than planned. Scatec Solar took the leading role for all EPC activities and managed the construction phase.
Operation and maintenance
Scatec Solar takes full responsibilities for all O&M services: monitor the plant, take corrective and preventive maintenance measures, reporting to utility and owners.
Scatec Solar Kalkbult Launch
Project highlights
First to be connected
- Project track record of nearly 1,000 MW
- Installed capacity of 519 MW
- A target to reach 3.5 GW in operation and under construction by year end 2021
- A project backlog and pipeline of 4.5 GW
Excellent performance
- Project track record of nearly 1,000 MW
- Installed capacity of 519 MW
- A target to reach 3.5 GW in operation and under construction by year end 2021
- A project backlog and pipeline of 4.5 GW
Targets exceeded
- Project track record of nearly 1,000 MW
- Installed capacity of 519 MW
- A target to reach 3.5 GW in operation and under construction by year end 2021
- A project backlog and pipeline of 4.5 GW
Socially responsible
- Project track record of nearly 1,000 MW
- Installed capacity of 519 MW
- A target to reach 3.5 GW in operation and under construction by year end 2021
- A project backlog and pipeline of 4.5 GW
Our values
“Companies and citizens drive the demand for clean and sustainable energy as the cost of pollution, power shortages and imports become self-evident”
Raymond Carlsen – CEO
Jan
2013
Successfully issued a NOK 500 million unsecured corporate green bond
April
2013
Commissioning of the 104 MW Red Hills solar plant in Utah, USA
May
2013
Commissioning of the 104 MW Red Hills solar plant in Utah, USA
Dec
2013
Successfully issued a NOK 500 million unsecured corporate green bond